About the project
International heavy cargo shipment from Liaoning Province, China, to a manufacturing facility in Saint Petersburg. The route covered over 8,700 km across three countries and required comprehensive logistics planning at every stage.
Key Project Parameters
Route: Anshan (China, Liaoning Province) — Saint Petersburg (Russia); over 8,700 km
Border crossings: Khorgos (China / Kazakhstan), Ozinki (Kazakhstan / Russia)
Execution period: August – September 2025; loading — 08.08.2025, delivery — 15.09.2025
Number of convoys: 1 (tractor + low-bed trailer)
Total cargo weight: 44.5 tonnes
Cargo characteristics
Equipment types: hub and lower rim are large-sized components of an industrial turbo unit.
Dimensions: length 14 m, width 6 m, height 2 m, weight 44,500 kg.
Transport: tractor unit coupled to a multi-axle low-bed trailer with a payload capacity of up to 100 tonnes and over 500 hp. Top loading and unloading.
Execution Details
Customs clearance: we organized export customs clearance from China and handled the opening and closing of transit channels through Kazakhstan and Russia. Cargo was placed at a temporary customs warehouse in Saratov Region (Balakovo customs post).
Technical documentation: a complete document package was prepared for the client — CMR, commercial invoice, packing list, warehouse receipt certificate, and a copy of the transit declaration.
Weight verification: re-weighing and confirmation of cargo weight and dimensions at the border before departure.
Cargo transshipment: at the China–Kazakhstan border warehouse, transfer of all cargo to the onward transport vehicle was organized.
Arrival notification: recipient notified at least 24 hours before delivery.
Results
Cargo delivered on 15 September 2025, fully on schedule.
- Safety of oversized industrial equipment maintained over 8,700+ km
- All delivery deadline and sequencing requirements met
- Full customs support across three countries: China, Kazakhstan, Russia
- Complete document package prepared and handed over to the client
The project demonstrated our competencies in:
- Organizations of international transportation of heavy and oversized cargo over long distances
- Customs clearance of complex industrial projects with transit through several countries
- Working with high-precision equipment for the energy industry
- Operational coordination of logistics in the face of tight deadlines and delivery requirements
The project, completed for the energy industry, included the delivery of key turbo-unit components to a large manufacturing facility, demonstrating our experience working with critical, full-cycle industrial equipment.
This case demonstrates the company's capabilities in organizing comprehensive international project shipments of any complexity—using specialized transport, a professional approach to logistics, and full documentation support.