Anshan → Saint Petersburg: Oversized Equipment Transport
Anshan → St. Petersburg: Transportation of Oversized Equipment

About the project

International heavy cargo shipment from Liaoning Province, China, to a manufacturing facility in Saint Petersburg. The route covered over 8,700 km across three countries and required comprehensive logistics planning at every stage.

Key Project Parameters

Route: Anshan (China, Liaoning Province) — Saint Petersburg (Russia); over 8,700 km
Border crossings: Khorgos (China / Kazakhstan), Ozinki (Kazakhstan / Russia)
Execution period: August – September 2025; loading — 08.08.2025, delivery — 15.09.2025
Number of convoys: 1 (tractor + low-bed trailer)
Total cargo weight: 44.5 tonnes

Cargo characteristics

Equipment types: hub and lower rim are large-sized components of an industrial turbo unit.
Dimensions: length 14 m, width 6 m, height 2 m, weight 44,500 kg.
Transport: tractor unit coupled to a multi-axle low-bed trailer with a payload capacity of up to 100 tonnes and over 500 hp. Top loading and unloading.

Execution Details

Customs clearance: we organized export customs clearance from China and handled the opening and closing of transit channels through Kazakhstan and Russia. Cargo was placed at a temporary customs warehouse in Saratov Region (Balakovo customs post). 

Technical documentation: a complete document package was prepared for the client — CMR, commercial invoice, packing list, warehouse receipt certificate, and a copy of the transit declaration.

Weight verification: re-weighing and confirmation of cargo weight and dimensions at the border before departure.

Cargo transshipment: at the China–Kazakhstan border warehouse, transfer of all cargo to the onward transport vehicle was organized.

Arrival notification: recipient notified at least 24 hours before delivery.

Results

Cargo delivered on 15 September 2025, fully on schedule.

  • Safety of oversized industrial equipment maintained over 8,700+ km
  • All delivery deadline and sequencing requirements met
  • Full customs support across three countries: China, Kazakhstan, Russia
  • Complete document package prepared and handed over to the client

The project demonstrated our competencies in:

  • Organizations of international transportation of heavy and oversized cargo over long distances
  • Customs clearance of complex industrial projects with transit through several countries
  • Working with high-precision equipment for the energy industry
  • Operational coordination of logistics in the face of tight deadlines and delivery requirements

The project, completed for the energy industry, included the delivery of key turbo-unit components to a large manufacturing facility, demonstrating our experience working with critical, full-cycle industrial equipment.

This case demonstrates the company's capabilities in organizing comprehensive international project shipments of any complexity—using specialized transport, a professional approach to logistics, and full documentation support.

Leave a request for a detailed consultation

We will prepare a full package of customs documents and ensure that control is passed without delays.
Discuss the Paperwork
Other projects
International transportation of large-sized heat exchange equipment Khorgos - Talimarjan
International transportation of large-sized heat exchange equipment Khorgos - Talimarjan
Planning and execution of international transport of large-scale industrial equipment — a condenser — from China to Uzbekistan. The cargo was delivered to an energy infrastructure facility in Talimarjan, Kashkadarya Region, Republic of Uzbekistan.
Project logistics for the supply of equipment for metallurgical production in Khorgos-Volzhsky (Project "RNK")
Project logistics for the supply of equipment for metallurgical production in Khorgos-Volzhsky (Project "RNK")
Organizing regular deliveries of equipment and materials from China to Russia for the construction of a modern production complex for the Russian Stainless Steel Company (RSC) in Volzhsky, Volgograd Region. NG-NEGABARIT acted as general freight forwarder for the project, ensuring an uninterrupted supply chain for large industrial equipment along the entire route.
Zoomlion 173 units of special equipment — China, Russia, Belarus
Zoomlion 173 units of special equipment — China, Russia, Belarus
73 units of heavy machinery. Two destinations: Russia and Belarus. A single continuous flow across the Eurasian Economic Union. When Zoomlion chose a partner for this operation, the task was clear but demanding: move an entire fleet out of the Khorgos plant and deliver every unit to its destination on time.
International transportation of industrial equipment from Khorgos to Nizhnekamsk
International transportation of industrial equipment from Khorgos to Nizhnekamsk
Planning and execution of a complex logistics operation for the large-scale delivery of process equipment from China to Russia for petrochemical production.
International transportation of super-heavy chemical equipment from Weihai to Veliky Novgorod
International transportation of super-heavy chemical equipment from Weihai to Veliky Novgorod
Organization and execution of an international shipment of super-heavy, oversized chemical equipment from China to Russia. The cargo—medium-temperature carbon monoxide converters—was delivered to a major chemical production complex in Veliky Novgorod.
Show more